Logan 200 North Construction
Logan 200 North Construction
The Logan City sewer replacement project is scheduled to begin in March. This work will complete essential upgrades to the sewer infrastructure along 200 and 400 North. The existing system has far exceeded its serviceable lifespan, making these improvements vital for ensuring reliable service to adjacent properties.
Phase 1 March-April 600 West to 350 West
Phase 2 April 350 West to 200 West
Phase 3 April-May 200 West to Main Street
The sewer pipeline is in the eastbound travel lane of 200 North. During construction only, westbound traffic will be allowed within each area of phasing. Please see the project website for the latest traffic control. Property access points may be briefly restricted during construction. Shoulder parking will be restricted. Please slow down and exercise caution near work zones marked by orange barrels and cones
The scheduled work will be done Monday-Friday mostly during daylight hours with occasional night work. Estimated completion is in mid-May.